Eskom returned Medupi Unit 4 to service on Sunday. However, its claim that this was eight months ahead of the original ...
Medupi Unit 4, has returned to service, adding 800 MW to the grid as part of Eskom’s plan to limit load shedding this winter.
Unit 4 of the Medupi Power Station was successfully returned to service on Sunday 6 July 2025, adding 800MW to the national grid.
Unit 4 at Medupi Power Station, which had been offline since August 8, 2021, was returned to service ahead of schedule.
Applications Open for the Eskom Youth Employment Programme. Eskom invites young, unemployed South Africans to apply for the ...
Eskom reports that, as of Friday, the weekly average breakdowns at its power stations were 14,496 MW. For eight weeks in a ...
Eskom restored Medupi Unit 4 early, adding 800 MW and helping end load-shedding • Coal still dominates South Africa’s power, slowing the energy transition • Eskom and industry are investing in ...
Medupi Unit 4 has been returned to service for the first time since August 2021 thanks to a Frankensteined Generator Statos ...
The chance of a return to load shedding this winter has been reduced after Eskom announced it reintegrated Medupi unit 4.
Eskom has reintegrated Unit 4 of the Medupi Power Station into the national grid, adding 800 megawatts of generation capacity ...
JOHANNESBURG - Eskom says Unit 4 of its Medupi power station has been successfully returned to service, eight months ahead of ...
Eskom has confirmed that it has a 5 GW pipeline of so-called ‘repowering’ projects at various stages of development on the ...